Question: Stanley's project is in execution. Stanley has a monthly stakeholder update meeting set up where he presents the project's progress and current issues to the


Stanley's project is in execution. Stanley has a monthly stakeholder update meeting set up where he presents the project's progress and current issues to the key stakeholders. During the last stakeholder update meeting, the stakeholders requested Stanley to provide bi-weekly project updates instead of monthly updates. The communication management plan has been broadly framed and it doesn't restrict Stanley from doing bi-weekly updates. What should Stanley do?

A. Start providing bi-weekly updates instead of monthly updates.

B. Update the communication management plan prior to providing the bi-weekly updates.

C. Disregard the stakeholders' request and continue with the monthly updates.

D. Request the stakeholders to submit a change request.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!