Question: Stanley's project is in execution. Stanley has a monthly stakeholder update meeting scheduled in which he presents the project's progress and current issues to the
Stanley's project is in execution. Stanley has a monthly stakeholder update meeting scheduled in which he presents the project's progress and current issues to the key stakeholders. During the last stakeholder update meeting, the stakeholders requested Stanley to provide biweekly project updates instead of monthly updates. The communication management plan has been broadly framed, and it does not restrict Stanley from doing bi-weekly updates. What should Stanley do?
Start providing bi-weekly updates instead of monthly updates Update the communication management plan prior to providing the bi-weekly updates Disregard the stakeholders' request and continue with the monthly updates Request that the stakeholders submit a change request
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
