Question: The approved project baseline should be changed: A. When a sequence of activities has taken longer than originally planned. B. To reflect approved project scope,
The approved project baseline should be changed: A. When a sequence of activities has taken longer than originally planned. B. To reflect approved project scope, cost, schedule, and technical changes. C. When the productivity within a certain discipline has been higher than originally planned. D. When a high-duration activity has been accomplished "out-of-sequence."
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
