Question: The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the BEST

The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the BEST thing for the project manager to do? A. Compress the schedule to recover the two weeks. B. Cut scope to recover the two weeks. C. Consult with the sponsor about options. D. Advise the client of the impact of the change.