Question: The client demanda chances to the product specification that will add only two week to the critical path. which of the following is the best

The client demanda chances to the product specification that will add only two week to the critical path. which of the following is the best thing for the project manager to do?

a. Compress the schedule to recover the two weeks. b. Cut scoope to recover the two weeks. c. Crash your project. d. Avise the client of the impact os the change.