Question: The client demanda chances to the product specification that will add only two week to the critical path. which of the following is the best
The client demanda chances to the product specification that will add only two week to the critical path. which of the following is the best thing for the project manager to do?
a. Compress the schedule to recover the two weeks. b. Cut scoope to recover the two weeks. c. Crash your project. d. Avise the client of the impact os the change.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
