Question: Two efficiency indicators that reflect the cost and schedule performance of a project are: A. Cost Projection Index (CPI) and Schedule Projection Index (SPI) B.


Two efficiency indicators that reflect the cost and schedule performance of a project are:

A. Cost Projection Index (CPI) and Schedule Projection Index (SPI)

B. Cost Performance Index (CPI) and Schedule Performance Index (SPI)

C. Actual Cost (AC) and Planned Value (PV)

D. Cost Pricing Index (CPI) and Schedule Performance Index (SPI)