Question: When developing your project schedule, you have asked everyone to provide a list of planned vacations over the next 3 months and you have applied
When developing your project schedule, you have asked everyone to provide a list of planned vacations over the next 3 months and you have applied this into the tasks that each person is responsible for. This is an example of what tool?
A. Resource Calendars B. Adjusting Leads C. Schedule Variances D. Adjusting Lags