Question: While developing your project schedule, you have asked everyone to provide a list of planned vacations over the next three months, and you have applied
While developing your project schedule, you have asked everyone to provide a list of planned vacations over the next three months, and you have applied this information to the tasks that each person is responsible for. What also needs updating?
Resource Calendars Leads Schedule Variances Lags