Question: When you review cost performance data on your project, different responses will be required depending on the degree of variance or control thresholds from the
When you review cost performance data on your project, different responses will be required depending on the degree of variance or control thresholds from the baseline. For example, a variance of 10 percent might not require immediate action, whereas a variance of 100 percent will require investigation. A description of how you plan to manage cost variances should be included in the—
a. Cost management plan
b. Change management plan
c. Performance measurement plan
d. Variance management plan