Question: Which process is MOST responsible for managing changes to the schedule components of the Project Management Plan? A. Control Schedule B. Create WBS C. Develop
Which process is MOST responsible for managing changes to the schedule components of the Project Management Plan?
A. Control Schedule B. Create WBS C. Develop Project Management Plan D. Develop Schedule