Question: While using the earned value management technique to measure project schedule progress on your project, you discover that your projects schedule performance index (SPI) is
While using the earned value management technique to measure project schedule progress on your project, you discover that your project’s schedule performance index (SPI) is 0.9. What does this mean?
A: The amount of buffer in your critical chain methodology is less than optimal.
B: The project network diagram was incorrectly put together.
C: The project is behind schedule and in need of schedule compression.
D: The project is ahead of schedule.