Question: You are a project manager on a project where your SPI has been calculated at .95. Your earned value (EV) has been calculated at $10,000,

You are a project manager on a project where your SPI has been calculated at .95. Your earned value (EV) has been calculated at $10,000, and your actual cost (AC) is $10,400, so what is your planned value (PV)?

A: $10,000 B: $10,526 C: $9,500 D: $10,947