You are currently preparing monthly status reports for your project and you are planning on reporting that the project has an SPI of 1.02 and a CPI of .83.
Your project sponsor approaches you and says that she has been given a directive by the CEO of the company to report only positive figures or else he is afraid the shareholders in the company will demand changes to the organization. You are confident that the next month’s status report will show a CPI greater than 1. What should you do?
A: Explain to your project sponsor the reasons why you believe the project reporting should be honest.
B: Report the CPI based on what you believe next months figures will be.
C: Resign from the project.
D: Report the project sponsor’s behavior to the CEO.