Question: You are currently preparing monthly status reports for your project and you are planning on reporting that the project has an SPI of 1.02 and

You are currently preparing monthly status reports for your project and you are planning on reporting that the project has an SPI of 1.02 and a CPI of .83.

Your project sponsor approaches you and says that she has been given a directive by the CEO of the company to report only positive figures or else he is afraid the shareholders in the company will demand changes to the organization. You are confident that the next month’s status report will show a CPI greater than 1. What should you do?

A: Explain to your project sponsor the reasons why you believe the project reporting should be honest.

B: Report the CPI based on what you believe next months figures will be.

C: Resign from the project.

D: Report the project sponsor’s behavior to the CEO.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!