Question: You are managing a complex project for a new method of heating and air conditioning in vehicles. You will use both solar and wind technologies
You are managing a complex project for a new method of heating and air conditioning in vehicles. You will use both solar and wind technologies in this project to reduce energy costs. Therefore, you must ensure that the work of your project will result in delivering the project’s specified scope, which means that you should measure completion of the product scope against the—
a. Scope management plan
b. Project management plan
c. Product requirements
d. Requirements management plan