Question: You are sequencing activities to develop the schedule using a precedence diagram method. To do this you need to identify the type of dependency between

You are sequencing activities to develop the schedule using a precedence diagram method. To do this you need to identify the type of dependency between the activities. Which of the following is not a type of dependency used in a precedence diagram method?

(a) Mandatory dependency

(b) Linear dependency

(c) Internal dependency

(d) External dependency