Question: You are sequencing activities to develop the schedule using a precedence diagram method. To do this you need to identify the type of dependency between
You are sequencing activities to develop the schedule using a precedence diagram method. To do this you need to identify the type of dependency between the activities. Which of the following is not a type of dependency used in a precedence diagram method?
(a) Mandatory dependency
(b) Linear dependency
(c) Internal dependency
(d) External dependency