Question: The project manager will use the PERT method of scheduling for the project that she is working on. Using the PERT calculation, the variance for
The project manager will use the PERT method of scheduling for the project that she is working on. Using the PERT calculation, the variance for the project is found to be 25 days and the duration of the project is found to be 169 days. What is the range of values for the project duration such that there will be at least a 95% probability that the actual project completion will fall between the high and low value of the range of values?
A. 164 - 173 days B. 144 - 194 days C. 119 - 219 days D. * 159 - 179 days