Question: You are working on a project to construct a new water treatment plant and are waiting on consents required from the government before you can
You are working on a project to construct a new water treatment plant and are waiting on consents required from the government before you can proceed with the work. During a meeting with a government employee to discuss the required consent, the employee mentions that the consent can be processed faster if you are willing to pay a processing fee. What is your BEST course of action?
A: Walk out of the meeting and notify your project sponsor.
B: Explain that you are not permitted to pay bribes.
C: Pay the fee if your project budget has allowed for it.
D: Ask the employee if he will accept goods instead of cash so you can hide the transaction better.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts