Question: Your project is halfway through its expected duration and has a CPI of 1.3 and an SPI of 1.2. Your project sponsor has told you

Your project is halfway through its expected duration and has a CPI of 1.3 and an SPI of 1.2. Your project sponsor has told you during a meeting that in her eyes the project is a failure because of the feedback she has been getting from important stakeholders on the project. You are surprised at this because the project is performing well financially and is ahead of schedule and you are sure the quality of the work you are completing is of a high standard and meets customer requirements. As the meeting closes, your project sponsor asks what you intend to do about the situation. Your BEST response would be what?

A: Revisit the manage stakeholder expectation process in your communications management plan.

B: Quit the project.

C: Say nothing.

D: Send out an e-mail to all stakeholders telling them how great the project is performing financially and time-wise.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!