Question: Greg is a key technical resource for your project. You've worked with Greg on past projects and have identified him as one of the team
Greg is a key technical resource for your project. You've worked with Greg on past projects and have identified him as one of the team members who will work on the project. The charter has been published, and there is great excitement about this project. You've scheduled a meeting to talk to Greg's manager next week about his participation on the project. Which of the following conditions does this describe?
A. Risk B. Assumption C. Deliverable D. Constraint