Question: Which person is responsible for authorizing the project to begin and for signing the project charter? A. Project sponsor B. Executive in the organization who
Which person is responsible for authorizing the project to begin and for signing the project charter?
A. Project sponsor B. Executive in the organization who requested the project C. Program manager D. Project manager