Question: You are developing a bottomup cost estimate for the first phase of your project. Which of the following is the most important input to complete
You are developing a bottom‐up cost estimate for the first phase of your project. Which of the following is the most important input to complete this task?
A. Historic data from a similar project B. Chart of accounts C. The WBS D. The scope statement