Question: Your selection committee has approved a project that requires specialized skills that are not available in the organization. This project has a tight timeline and
Your selection committee has approved a project that requires specialized skills that are not available in the organization. This project has a tight timeline and you are looking for ways to get resources on board as quickly as possible. Which of the following will help you speed up the procurement of resources? (Choose two.)
A. Preexisting contract B. Predetermined clients C. Prequalified vendor list D. Predetermined selection process