Question: A project budget identifies $5,000 budgeted for programming costs. The actual amount for programming costs is $5,450. Which of the following statements is correct? a.

A project budget identifies $5,000 budgeted for programming costs. The actual amount for programming costs is

$5,450. Which of the following statements is correct?

a. The $450 represents a negative variance to the budget

b. There is no variance to the budget

c. The $450 represents a positive variance to the budget

d. The entire $5,450 represents a positive variance to the budget

Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

cThe overrun of ... View full answer