Question: A project budget identifies $5,000 budgeted for programming costs. The actual amount for programming costs is $5,450. Which of the following statements is correct? a.
A project budget identifies $5,000 budgeted for programming costs. The actual amount for programming costs is
$5,450. Which of the following statements is correct?
a. The $450 represents a negative variance to the budget
b. There is no variance to the budget
c. The $450 represents a positive variance to the budget
d. The entire $5,450 represents a positive variance to the budget