If a worker earns $30 per hour in salary but the project is charged $75 per hour for each hour
Question:
If a worker earns $30 per hour in salary but the project is charged $75 per hour for each hour the individual works, then the overhead rate is:
A. 100%
B. 150%
C. 250%
D. None of the above
This problem has been solved!
Do you need an answer to a question different from the above? Ask your question!
Step by Step Answer:
Related Book For
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9781119805373
13th Edition
Authors: Harold Kerzner
Question Details
Chapter #
13- Pricing and Estimating
Section: Multiple Choice
Problem: 6
View Solution