Question: Resource leveling is a method to: a. Make sure everyone working on the project has approximately the same amount of work to accomplish b. A
Resource leveling is a method to:
a. Make sure everyone working on the project has approximately the same amount of work to accomplish
b. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply
c. Use a calendar to identify the working days and shifts on which each specific resource is available
d. None of the above
Step by Step Solution
3.39 Rating (161 Votes )
There are 3 Steps involved in it
bresource leveling i... View full answer