Suppose that you are a project manager asked to develop the network activity diagram and identify the
Question:
Suppose that you are a project manager asked to develop the network activity diagram and identify the critical path for a project based on the following information. Draw the activity network as a Gantt chart. What is the expected duration of the project?
Transcribed Image Text:
Activity Expected Duration Predecessors 1. Design 3 days 2. Specification 5 days 1 3. Draw up contract 2 days 1,2 4. Client meeting 1 day 2,3 5. Project launch 1 day 4 6. Software development 15 days 3 7. Testing 11 days 8. Refine 5 days 69 6 9. Present to client 1 day 8
Step by Step Answer:
This question has not been answered yet.
You can Ask your question!
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9781292269146
5th Global Edition
Authors: Jeffrey K.Pinto
Question Posted:
Students also viewed these Business questions
-
Develop the network activity chart and identify the critical path for a project based on the following information. Draw the activity network as a Gantt chart. What is the expected duration of the...
-
As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you...
-
Search for news that is no more than one year old, from reliable sources, and that are able to help you answer what is requested in the sections, about the current economic situation in China. If you...
-
The manufactured wood beam carries a uniformly distributed load of in- tensity wo. Determine the largest safe value of wo if the maximum shear stress in the wood is limited to 300 psi. 1.0 ft Wo 4 ft...
-
Many consumers want to recycle, but rules vary among localities making it difficult for consumers to know if something is recyclable. Voluntary "How2Recycle" labels are starting to appear on products...
-
The voltage generated in one phase of an unloaded three-phase synchronous generator is of the form v(t) = Vo cos cot. Write expressions for the voltage in the remaining two phases.
-
Pileri Industries shipped goods to Consolidated Industries, Inc., via a common carrier. The goods were lost in transit. Pileri claimed that the sale was a shipment contract, thus putting the risk of...
-
A partial balance sheet and income statement for King Corporation follow: KING CORPORATION Partial Balance Sheet December 31, 2009 Assets Current assets: Cash .........................$ 33,493...
-
You have calculated the historical dollar weighted return, annual geometric average return and annual arithmetic average return. You always reinvest your dividends and interest earned on the...
-
Reconfigure the Gantt chart in Problem 10.13 to include some different predecessor relationships. Optional: Solve this problem with Microsoft Project. a. Assume that activities B and C are linked...
-
Given the following information, answer the questions about this project: a. Draw the network as a Gantt chart. b. What is the critical path? Which activities have slack time? c. What would happen if...
-
A study reports that recent college graduates from New Hampshire face the highest average debt of $31,048 (The Boston Globe, May 27, 2012). A researcher from Connecticut wants to determine how recent...
-
One of the operating activities Mary could do to avoid another cash flow crisis would be to increase the sale of products in her business or increase the price. This could be by adding more pastries...
-
2020 Dec Firm (enterprise) value 19649 Total debt 18675 Cash 895 Equity value 1869 WACC 10.3% Long-term growth 2.0% The private equity fund is planning to invest 2000 in cash in this deal in December...
-
Data analytics performed to identify the most profitable customers would be most likely to affect which income statement account?Data analytics performed to identify the most profitable customers...
-
Conduct an analysis of delivered costs of crude oil ($US/ barrel) from 3 different crude oil production basin or trading hub to at least 1 destination market i.e. 1 refinery area. Use multiple...
-
1. Show that the following grammar is ambiguous: SAU SVC UBC V AB A a A f B b C c Cg where upper case letters are nonterminals, lower case letters are terminals, and S is the start symbol. Give an...
-
A point A is located on the rim of a wheel of radius R = 0.50 m which rolls without slipping along a horizontal surface with velocity v = 1.00 m/s. Find: (a) The modulus and the direction of the...
-
A handrail, which weighs 120 N and is 1.8 m long. was mounted to a wall adjacent to a small set of steps (Figure P4.26). The support at A has broken, and the rail has fallen about the loose bolt at 8...
-
What do the Schedule Performance Index (SPI) and the CostPerformance Index (CPI) demonstrate? How can a project manager use this information to estimate future project performance?
-
Suppose the SPI is calculated as less than 1.0. Is this good news or bad newsfor the project? Why?
-
1) Suppose you were a consultant called into the project by the federal government in 1990, when it still seemed viable. Given the start to the project, what steps would you have taken to reintroduce...
-
12:57 2. Knowledge Management Exam 202... DOCX-75 KB In 2002, after almost 50 years of performing, the Calgary Philharmonic Orchestra (CPO), Canada's fifth-largest, was seeking bankruptcy protection...
-
You deposit $ 5 0 0 in a savings account paying 1 . 5 % simple interest.How much interest will you earn in 4 years?How much is in the account at the end of 4 years?
-
A company is considering investing in a project. The future perpetual cash flow is either $ 7 5 0 K if the market goes up or $ 1 2 5 K if the market goes down next year. The objective probability the...
Study smarter with the SolutionInn App