Given the following information, answer the questions about this project: a. Draw the network as a Gantt

Question:

Given the following information, answer the questions about this project:image text in transcribed

a. Draw the network as a Gantt chart.

b. What is the critical path? Which activities have slack time?

c. What would happen if activities B and D each took 5 extra days to complete instead of the expected duration?
How would the critical path change?