Question: Use the following data to answer the questions that follow. Average velocity = (Remaining effort Day 1 - Remaining effort Current Day)/(Current Day 2 Day

Use the following data to answer the questions that follow.

Sprint Day 1 2 3 4 1.0 75 5 6 8 Remaining


Average velocity = (Remaining effort Day 1 - Remaining effort Current Day)/(Current Day 2 Day 1) Estimated completion date 5 Current Day 1 (Remaining effort/Average velocity)
a. Create a burndown chart for the given data using Excel or the software of your choice.
b. What is the average velocity for the project, in story points per day? (Assume the Current Day is Day 3).
c. What is the project’s expected completion date?

Sprint Day 1 2 3 4 1.0 75 5 6 8 Remaining effort (story points) 75 55 45 0 0 0 0 0

Step by Step Solution

3.53 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!