Question: Using the data below, create a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just as
Using the data below, create a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just as the monthly and cumulative costs are shown in Exhibit 10.9.

Immediate Duration Hourly Work Hours Activity Predecessor in Days Resource Cost per Day A Evaluate freezers 2 Alcides $45 6 B Chart temperatures 6 Joan $50 4 C Review service record 2 Alcides D Consult with HVAC engineer A, B, C 3 Alcides E Develop construction plan D 10 Joan F Complete IC assignment E 2 Alcides G Complete ROI analysis E 5 Joan H Conduct regulatory review E 4 Joan I Obtain construction approval F, G, H 2 Alcides