Question: 1. Using the data below, make a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just

1. Using the data below, make a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just as the monthly and cumulative costs are shown below:

Activity Immediate Predecessor Duration in Days Resource Hourly Cost Work Hours per Day
A Evaluate freezers 2 Alcides $45
B Chart temperatures 6 Joan $50
C Review service record 2 Alcides
D Consult with HVAC engineer A, B, C 3 Alcides
E Develop construction plan D 10 Joan
F Complete IC assignment E 2 Alcides
G Complete ROI analysis E 5 Joan
H Conduct regulatory review E 4 Joan
I Obtain construction approval F, G, H 2 Alcides

2. Using the data below, make a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just as the monthly and cumulative costs are shown below:

In addition to the questions above, answer the following questions based on the date provided in the exercises and your analysis.

  • Determine the unconstrained critical path and its length.
    • Note: Use days for question 2 and weeks for question 3. Use project days only, no weekends.
  • Determine the total hours and the hours per person required to complete the work.
  • Determine the total labor cost and the labor cost per person.
  • Prepare a figure similar to Exhibit 10.9 in the text, illustrating a cumulative cost curve.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!