Question: Using the data below, create a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just as
Using the data below, create a time-phased budget for the project. Show how much the daily and cumulative costs for the project are, just as the monthly and cumulative costs are shown inExhibit 10.9
| WBS | Activity | Immediate Predecessor | Duration in Weeks | Resource | Hourly Cost | Hours per Week |
|---|---|---|---|---|---|---|
| 1 | Operational definition | |||||
| 1.1 | Research literature | 3 | Becky | $35 | 30 | |
| 1.2 | Identify and define terms | 1.1 | 1 | Ann | $60 | 30 |
| 1.3 | Obtain approval of definition | 1.2 | 2 | Clive | $50 | 20 |
| 2 | Target Selection | |||||
| 2.1 | Solicit partners for pilot | 2 | Ann | |||
| 2.2 | Hold brainstorming meeting | 2.1 | 2 | Becky | ||
| 2.3 | Identify characteristics of targets | 2.2, 3.1 | 1 | Ann | ||
| 2.4 | Obtain approval of partners | 2.3, 1.2, 3.4 | 1 | Clive | ||
| 3 | Question set | |||||
| 3.1 | Identify process group members | 2 | Clive | |||
| 3.2 | Develop question set | 2.3 | 4 | Ann | ||
| 3.3 | Prototype and validate question set | 3.2 | 3 | Becky | ||
| 3.4 | Add partners | 3.1, 2.1 | 3 | Becky | ||
| 4 | Pilot process | |||||
| 4.1 | Schedule with target audience | 2.4 | 2 | Becky | ||
| 4.2 | Conduct beta test | 3.4, 2.4 | 2 | Clive | ||
| 4.3 | Process feedback from target audience | 4.2 | 2 | Ann | ||
| 4.4 | Conduct pilot | 4.3 | 2 | Clive | ||
| 4.5 | Analyze results | 4.4 | 2 | Clive |