Question: Using the information in Problem 13.15, highlight the projects status on day 14 but assume that activity D has not yet begun. What would the
Using the information in Problem 13.15, highlight the project’s status on day 14 but assume that activity D has not yet begun. What would the new tracking Gantt chart show? Print the output file.
Problem 13.15
Use the following information to construct a tracking Gantt chart using MS Project.
Highlight project status on day 14 using the tracking option and assuming that all tasks to date have been completed on time. Print the output file.
Activities Duration Preceding Activities A 5 days none B 4 days A C 3 days A D 6 days B, C E 4 days B F 2 days D, E