Question: Using the data in the table below, calculate the project schedule variance units: Schedule Variance Work Units A B C D E Total Planned Value
Using the data in the table below, calculate the project schedule variance units:
Schedule Variance Work Units A B C D E Total Planned Value (PV) 30 25 10 15 40 120 Earned Value (EV) 25 15 5 15 30 Schedule Variance (SV)
Step by Step Solution
3.50 Rating (153 Votes )
There are 3 Steps involved in it
To determine the Schedule variance for each of the units we can ap... View full answer
Get step-by-step solutions from verified subject matter experts
