Your project team is working on a brand-new project with leading-edge technology. As a result, it is

Question:

Your project team is working on a brand-new project with leading-edge technology. As a result, it is very difficult for your team to give reasonable accurate estimates for how long their activities are going to take in order to be completed.

Because of this uncertainty, it would be appropriate for you to require team members to use what kind of logic when estimating durations?

a. Normal distribution

b. Beta distribution

c. Deterministic estimates

d. Experience