A building contractor is working on a vacation home and is looking over his schedule. He notices

Question:

 A building contractor is working on a vacation home and is looking over his schedule. He notices that the schedule calls for the foundation footers to be poured and then the rough floor decking to be installed. In this plan, the decking would be an example of what type of activity?

a. Successor task

b. Predecessor task

c. Lag activity

d. Crashed activity