Question: 9. A network for a small project is shown below. (duration, men) ~ A (7,7) [2lQ] H (7,5) [ill] D 8,6 E (7,5) WIQJ ~
9. A network for a small project is shown below.
(duration, men) ~\ A (7,7)
[2lQ]
H (7,5)
[ill]
D 8,6 E (7,5)
WIQJ ~ 9 8(3,5) ~ 1(4,10c;f C (4,6)\..::../ ~~ K (5,9) oG(9,4) .~~ 8
~ ~ C±TIJ [i]J]
a. Develop a resource schedule using a limit of 15 men/ day.
b. Solve the problem using Microsoft Project and show total project duration. Attempt to reduce project duration by assigning random priorities to the tasks.
c. Modify the Sch-Level.xls file to consider the data of this exercise. Use Evolver to solve the problem and print your Excel model. Draw a modified network that corresponds to your optimum solution.