Question: 8. A network for a small project is shown below. @@ }----'-'---'-~ 5 Activity (duration, men) C(5,8) 1(3,7) a. Develop a resource schedule using a

8. A network for a small project is shown below.

@@

}----'-'---'-~ 5 Activity (duration, men)

C(5,8) 1(3,7)

a. Develop a resource schedule using a limit of 20 men.

b. Solve the problem using Microsoft Project and show total project duration. Attempt to reduce project duration by assigning random priorities to the tasks.

c. Modify the Sch-Level.xls file to consider the data of this exercise. Use Evolver to solve the problem and print your Excel model. Draw a modified network that corresponds to your optimum solution.