Question: A contingency reserve is ____________. A. An active risk acceptance response B. Determined by a risk audit C. A passive risk acceptance response D. Not
A contingency reserve is ____________.
A. An active risk acceptance response B. Determined by a risk audit C. A passive risk acceptance response D. Not a risk response strategy