Question: A large process reengineering project is halfway done and is showing a CPI of 1.3 and a SPI of 0.75. How should the project manager
A large process reengineering project is halfway done and is showing a CPI of 1.3 and a SPI of 0.75. How should the project manager proceed to realign the project with its baselines?
A. Use the management reserve.
B. Crash the schedule.
C. Reduce the product scope.
D. Issue a change request to extend the project schedule.