Question: A key stakeholder has submitted a change request which will not impact the project schedule. What should the project manager do NEXT? A. Approve the
A key stakeholder has submitted a change request which will not impact the project schedule.
What should the project manager do NEXT? A. Approve the change request and engage the project team to start the implementation procedure.
B. Seek help from the Change Control Board.
C. Ask the sponsor to authorize the change request.
D. Evaluate the impacts of change on other project constraints.