Question: A key stakeholder has submitted a change request which will not impact the project schedule. What should the project manager do NEXT? A. Approve the

A key stakeholder has submitted a change request which will not impact the project schedule.

What should the project manager do NEXT? A. Approve the change request and engage the project team to start the implementation procedure.

B. Seek help from the Change Control Board.

C. Ask the sponsor to authorize the change request.

D. Evaluate the impacts of change on other project constraints.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!