Question: A program manager uses a diagram to prepare a snapshot of the status of various projects occurring in the organization that he is managing. Which

A program manager uses a diagram to prepare a snapshot of the status of various projects occurring in the organization that he is managing.

Which diagram or chart does the program manager uses?

A. Milestone Chart B. Burndown Chart C. Histogram D. Pie-Chart