Question: A project manager has received some help from the team, and she needs help from them again so that she can create a detailed project
A project manager has received some help from the team, and she needs help from them again so that she can create a detailed project budget. Which project management process group is she in?
A. Initiating B. Before the project management process C. Planning D. Executing