Question: A table of risks, their probability, impact, and a number representing the overall risk score is called a ________________. A. Risk table B. Risk matrix


A table of risks, their probability, impact, and a number representing the overall risk score is called a ________________.

A.

Risk table B.

Risk matrix C.

Quantitative matrix D.

Qualitative matrix