Question: During execution, one key stakeholder requests the project manager for a change in a work package for which work has not started yet. What should
During execution, one key stakeholder requests the project manager for a change in a work package for which work has not started yet.
What should the project manager do NEXT?
A. Ask the stakeholder to raise a formal change request. B. Update the work package and the project management plan. C. Document the stakeholder request in the assumption log. D. Document the change request in the change log.