Question: During execution, you have identified that the raw materials supplied to you are of a low grade than expected. What should the project manager do
During execution, you have identified that the raw materials supplied to you are of a low grade than expected.
What should the project manager do FIRST?
A. Review the Quality Management Plan. B. Update the Project Document.
C. Create a workaround.
D. Review the Requirement Documentation.