Question: During the Approve, Estimate, and Commit User-Stories Process, the Scrum Team must estimate the effort and time required for each Task. A) _TRUE_ B) _FALSE_
During the “Approve, Estimate, and Commit User-Stories” Process, the Scrum Team must estimate the effort and time required for each Task.
A) _TRUE_ B) _FALSE_ ANSWER: A