Question: During the Create Tasks Process, the Scrum Team must decide on and develop the Task list for each of the User-Stories, while taking into consideration
During the Create Tasks Process, the Scrum Team must decide on and develop the Task list for each of the User-Stories, while taking into consideration any dependencies among them.
A) _TRUE_ B) _FALSE_ ANSWER: A