Question: During the Create Deliverables Process, the Scrum Master must support the Scrum Team and help them create the current Sprints Deliverables, and update the ScrumBOARD
During the Create Deliverables Process, the Scrum Master must support the Scrum Team and help them create the current Sprint’s Deliverables, and update the ScrumBOARD and the Impediment Log Document.
A) _TRUE_ B) _FALSE_ ANSWER: A