Question: Expected Monitory Value (EMV) is used to rank Risks by their expected Monitory Values. A Risk expected Monitory Value is calculated by multiplying the Risk

Expected Monitory Value (EMV) is used to rank Risks by their expected Monitory Values. A Risk expected Monitory Value is calculated by multiplying the Risk Impact in Dollars with its Probability in Percentage.

A) _TRUE_ B) _FALSE_ ANSWER: A