Question: If a Change Request is received from the Project Team, then such CHANGEREQUESTS can slightly impact the Project Schedule and/or Specifications. A) _TRUE_ B) _FALSE_
If a Change Request is received from the Project Team, then such CHANGEREQUESTS can slightly impact the Project Schedule and/or Specifications.
A) _TRUE_ B) _FALSE_ ANSWER: A